LETTING DATNH-9130(00)E MAINE DEPARTMENT OF TRANSPORTATION DATE : 12/04/01
PAGE : 1
LOCATION : CHINA TABULATION OF BIDS
PALERMO
CONTRACT ID : 007772.00
=========
COMPLETION DATE : 10/21/00
PROJECT(S): STP-7772(00)X COUNTIE(S) : KENNEBEC MAINE STATE DEPTARTMENT OF TRANSPORTATION
A TRUE COPY : __________________________
TITLE : __________________________
CONTRACT DESCRIPTION : LEVEL 1 RESURFACING ATTEST : _______________________________
NOTARY PUBLIC
--------------------------------------------------------------------------------------------------------------------------
TOTAL % OVER
RANK VENDOR NO./NAME BID LOW BID
--------------------------------------------------------------------------------------------------------------------------
1 000529 BARRETT PAVING MATERIALS, INC. $ 1,288,840.39 100.0000%
2 000059 PIKE INDUSTRIES, INC. $ 1,355,662.46 105.1847%
====================================================================================================================================
|( 1 ) 000529 |( 2 ) 000059 |( )
|BARRETT PAVING MATERIALS, I |PIKE INDUSTRIES, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001 HIGHWAY ITEMS
| | |
0010 107.27 LUMP| 12500.00000 12500.00| 29670.00000 29670.00|
TEMPORARY SOIL EROSION AND WATER | | |
POLLUTION CONTROL | | |
0040 202.203 2185.000 M2 | 16.60000 36271.00| 25.00000 54625.00|
PAVEMENT BUTT JOINTS | | |
0060 203.202 4772.000 M | 6.95000 33165.40| 8.00000 38176.00|
INSLOPE EXCAVATION | | |
0070 203.203 3035.000 M | 7.25000 22003.75| 11.00000 33385.00|
DITCH EXCAVATION | | |
0080 403.209 130.000 MG | 125.00000 16250.00| 90.00000 11700.00|
HOT MIX ASPHALT 9.5 MM(SIDEWALKS,DRIVES | | |
INCIDENTAL ) | | |
0090 403.210 15860.000 MG | 43.20000 685152.00| 39.00000 618540.00|
HOT MIX ASPHALT 9.5 MM NOMINAL MAX SIZE | | |
0100 403.211 1950.000 MG | 44.60000 86970.00| 39.00000 76050.00|
HOT MIX ASPHALT (SHIM) | | |
0110 403.212 3750.000 MG | 42.95000 161062.50| 39.00000 146250.00|
HOT MIX ASPHALT 4.75 MM | | |
0120 409.15 16990.000 L | 0.30000 5097.00| 0.80000 13592.00|
BITUMINOUS TACK COAT APPLIED | | |
0130 411.10 200.000 M3 | 63.30000 12660.00| 65.00000 13000.00|
UNTREATED AGGREGATE SURFACE COURSE | | |
(TRUCK MEASURE) | | |
LETTING DATE : 05/03/00 MAINE DEPARTMENT OF TRANSPORTATION DATE : 12/04/01
PAGE : 2
LOCATION : CHINA TABULATION OF BIDS
PALERMO
CONTRACT ID : 007772.00
=========
====================================================================================================================================
|( 1 ) 000529 |( 2 ) 000059 |( )
|BARRETT PAVING MATERIALS, I |PIKE INDUSTRIES, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0140 604.13 1.000 EA | 1870.00000 1870.00| 1600.00000 1600.00|
600 MM CATCH BASIN TYPE E | | |
0150 604.182 2.000 EA | 165.00000 330.00| 300.00000 600.00|
CLEAN EXISTING CATCH BASIN AND MANHOLE | | |
0160 606.17 391.200 M | 34.60000 13535.52| 34.00000 13300.80|
GUARDRAIL TYPE 3B - SINGLE RAIL | | |
0170 606.178 57.150 M | 17.05000 974.41| 16.75000 957.26|
GUARDRAIL BEAM | | |
0180 606.21 41.800 M | 38.65000 1615.57| 37.75000 1577.95|
GUARDRAIL TYPE 3B - 4.5 M RADIUS OR LES | | |
0190 606.22 38.100 M | 37.90000 1443.99| 37.00000 1409.70|
GUARDRAIL TYPE 3B - OVER 4.5 M RADIUS | | |
0200 606.35 10.000 EA | 22.00000 220.00| 25.00000 250.00|
GUARDRAIL DELINEATOR POST | | |
0210 606.367 10.000 EA | 29.70000 297.00| 30.00000 300.00|
REPLACE UNUSABLE EXISTING GUARDRAIL | | |
POSTS | | |
0220 606.754 20.000 EA | 880.00000 17600.00| 1000.00000 20000.00|
WIDEN SHOULDER FOR 350 END TREATMENT | | |
0230 606.79 20.000 EA | 1420.00000 28400.00| 1500.00000 30000.00|
GUARDRAIL 350 FLARED TERMINAL | | |
0240 609.31 185.000 M | 10.85000 2007.25| 15.00000 2775.00|
CURB TYPE 3 | | |
0250 613.319 3650.000 M2 | 1.10000 4015.00| 2.00000 7300.00|
TEMPORARY EROSION CONTROL BLANKET | | |
0260 618.1401 325.000 UN | 13.50000 4387.50| 14.00000 4550.00|
SEEDING METHOD NUMBER 2 - PLAN QUANTITY | | |
0270 619.12 6.000 UN | 7.10000 42.60| 22.00000 132.00|
MULCH | | |
0280 619.1201 319.000 UN | 7.10000 2264.90| 22.00000 7018.00|
MULCH - PLAN QUANTITY | | |
0290 627.71 245.000 M | 2.70000 661.50| 2.75000 673.75|
100 MM WHITE PAVEMENT MARKING LINE | | |
0300 627.73 120.000 M | 5.40000 648.00| 5.25000 630.00|
100 MM YELLOW PAVEMENT MARKING LINE | | |
0310 627.75 7.500 M2 | 71.00000 532.50| 70.00000 525.00|
WHITE OR YELLOW PAVEMENT AND CURB | | |
MARKING | | |
0320 627.76 LUMP| 4950.00000 4950.00| 6500.00000 6500.00|
TEMPORARY PAVEMENT MARKING LINE, WHITE | | |
OR YELLOW | | |
LETTING DATE : 05/03/00 MAINE DEPARTMENT OF TRANSPORTATION DATE : 12/04/01
PAGE : 3
LOCATION : CHINA TABULATION OF BIDS
PALERMO
CONTRACT ID : 007772.00
=========
====================================================================================================================================
|( 1 ) 000529 |( 2 ) 000059 |( )
|BARRETT PAVING MATERIALS, I |PIKE INDUSTRIES, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0330 627.77 275.000 M2 | 29.60000 8140.00| 28.00000 7700.00|
REMOVING PAVEMENT MARKINGS | | |
0340 629.05 15.000 MH | 34.15000 512.25| 25.00000 375.00|
HAND LABOR, STRAIGHT TIME | | |
0350 631.12 15.000 HR | 94.55000 1418.25| 90.00000 1350.00|
ALL PURPOSE EXCAVATOR (INCLUDING | | |
OPERATOR) | | |
0360 631.172 20.000 HR | 55.00000 1100.00| 45.00000 900.00|
TRUCK - LARGE (INCLUDING OPERATOR) | | |
0370 639.19 1.000 EA | 4700.00000 4700.00| 6000.00000 6000.00|
FIELD OFFICE TYPE B | | |
0380 645.292 3.000 M2 | 75.00000 225.00| 1300.00000 3900.00|
REGULATORY, WARNING, CONFIRMATION AND | | |
ROUTE MARKER ASSEMBLY SIGNS TYPE II | | |
0390 652.31 15.000 EA | 99.00000 1485.00| 100.00000 1500.00|
TYPE I BARRICADE | | |
0400 652.33 15.000 EA | 22.00000 330.00| 60.00000 900.00|
DRUM | | |
0410 652.34 100.000 EA | 15.40000 1540.00| 16.00000 1600.00|
CONE | | |
0420 652.35 135.000 M2 | 44.00000 5940.00| 80.00000 10800.00|
CONSTRUCTION SIGNS | | |
0430 652.36 108.000 CD | 170.00000 18360.00| 175.00000 18900.00|
MAINTENANCE OF TRAFFIC CONTROL DEVICES | | |
0440 652.38 2250.000 MH | 12.65000 28462.50| 15.00000 33750.00|
FLAGGER | | |
0450 659.10 LUMP| 59700.00000 59700.00| 132900.00000 132900.00|
MOBILIZATION | | |
SECTION TOTALS | $ 1,288,840.39| $ 1,355,662.46| $ 0.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
CONTRACT TOTALS | $ 1,288,840.39| $ 1,355,662.46| $
====================================================================================================================================