     LETTING DATE : 04/05/00                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/04/01
                                                                                                                   PAGE : 1
     LOCATION : FORKSTOWN TWP.                          TABULATION OF BIDS
                TWP A R 02 WELS
                                            CONTRACT ID : 009053.00
                                                          =========

                                        COMPLETION DATE : 09/16/00

   PROJECT(S):  STP-9053(00)X           COUNTIE(S) : AROOSTOOK                   MAINE STATE DEPTARTMENT OF TRANSPORTATION

                                                                                 A TRUE COPY : __________________________

                                                                                       TITLE : __________________________

     CONTRACT DESCRIPTION : LEVEL 2 RESURFACING                                  ATTEST : _______________________________
                                                                                                 NOTARY PUBLIC
  --------------------------------------------------------------------------------------------------------------------------
                                                                                                   TOTAL         % OVER
  RANK     VENDOR NO./NAME                                                                          BID           LOW BID
  --------------------------------------------------------------------------------------------------------------------------
   1   000022         THE LANE CONSTRUCTION CORP.                                            $    691,250.65     100.0000%
   2   000351         COUNTY CONCRETE & CONSTRUCTION CO., INC.                               $    817,802.40     118.3077%
====================================================================================================================================
                                          |(   1  ) 000022             |(   2  ) 000351             |(      )
                                          |THE LANE CONSTRUCTION CORP. |COUNTY CONC. & CONSTR. CO.  |
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001   HIGHWAY ITEMS
                                          |                            |                            |
0010 107.27                           LUMP|   10000.00000      10000.00|   10000.00000      10000.00|
  TEMPORARY SOIL EROSION AND WATER        |                            |                            |
  POLLUTION CONTROL                       |                            |                            |
0020 202.203                 110.000  M2  |       8.00000        880.00|       8.00000        880.00|
  PAVEMENT BUTT JOINTS                    |                            |                            |
0030 203.202                5260.000  M   |       4.60000      24196.00|       7.50000      39450.00|
  INSLOPE EXCAVATION                      |                            |                            |
0040 203.203                1340.000  M   |       6.60000       8844.00|       8.50000      11390.00|
  DITCH EXCAVATION                        |                            |                            |
0050 203.25                   25.000  M3  |      18.00000        450.00|       7.50000        187.50|
  GRANULAR BORROW                         |                            |                            |
0060 204.20                26610.000  M2  |       2.80000      74508.00|       3.50000      93135.00|
  ADD SHOULDER AGGREGATE TO EXISTING      |                            |                            |
  SHOULDER, PLAN QUANTITY                 |                            |                            |
0070 304.103                 164.000  M3  |      35.00000       5740.00|       7.50000       1230.00|
  AGGREGATE SUBBASE - GRAVEL (TRUCK       |                            |                            |
  MEASURE)                                |                            |                            |
0080 307.32                21070.000  M2  |       2.80000      58996.00|       3.50000      73745.00|
  COLD IN-PLACE RECYCLED MATERIAL         |                            |                            |
  (UNTREATED) TRAVELWAY                   |                            |                            |
0090 403.208                2530.000  MG  |      39.00000      98670.00|      43.00000     108790.00|
  HOT MIX ASPHALT 12.5 MM NOMINAL MAX SIZ |                            |                            |
0100 403.209                   5.000  MG  |      90.00000        450.00|     100.00000        500.00|
  HOT MIX ASPHALT 9.5 MM(SIDEWALKS,DRIVES |                            |                            |
  INCIDENTAL )                            |                            |                            |
     LETTING DATE : 04/05/00                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/04/01
                                                                                                                   PAGE : 2
     LOCATION : FORKSTOWN TWP.                          TABULATION OF BIDS
                TWP A R 02 WELS
                                            CONTRACT ID : 009053.00
                                                          =========

====================================================================================================================================
                                          |(   1  ) 000022             |(   2   ) 000351            |(      )
                                          |THE LANE CONSTRUCTION CORP. |COUNTY CONC. & CONSTR. CO.  |
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0110 403.210                4480.000  MG  |      39.00000     174720.00|      43.00000     192640.00|
  HOT MIX ASPHALT 9.5 MM NOMINAL MAX SIZE |                            |                            |
0120 403.211                3000.000  MG  |      39.00000     117000.00|      43.00000     129000.00|
  HOT MIX ASPHALT (SHIM)                  |                            |                            |
0130 409.15                 3280.000  L   |       1.00000       3280.00|       1.40000       4592.00|
  BITUMINOUS TACK COAT APPLIED            |                            |                            |
0140 411.10                   20.000  M3  |      36.00000        720.00|      27.00000        540.00|
  UNTREATED AGGREGATE SURFACE COURSE      |                            |                            |
  (TRUCK MEASURE)                         |                            |                            |
0150 603.16                   18.280  M   |      35.00000        639.80|      80.00000       1462.40|
  375 MM CULVERT PIPE OPTION I            |                            |                            |
0160 603.17                   36.560  M   |      45.00000       1645.20|      95.00000       3473.20|
  450 MM CULVERT PIPE OPTION I            |                            |                            |
0170 603.179                  45.110  M   |      75.00000       3383.25|     120.00000       5413.20|
  450 MM CULVERT PIPE OPTION III          |                            |                            |
0180 603.189                   2.000  M   |      95.00000        190.00|     130.00000        260.00|
  525 MM CULVERT PIPE OPTION III          |                            |                            |
0190 603.199                  85.340  M   |      85.00000       7253.90|     190.00000      16214.60|
  600 MM CULVERT PIPE OPTION III          |                            |                            |
0200 610.08                   27.000  M3  |      30.00000        810.00|      75.00000       2025.00|
  PLAIN RIPRAP                            |                            |                            |
0210 613.319                1614.000  M2  |       3.00000       4842.00|       1.75000       2824.50|
  TEMPORARY EROSION CONTROL BLANKET       |                            |                            |
0220 618.1401                290.000  UN  |      14.50000       4205.00|      40.00000      11600.00|
  SEEDING METHOD NUMBER 2 - PLAN QUANTITY |                            |                            |
0230 619.1201                290.000  UN  |       9.75000       2827.50|      20.00000       5800.00|
  MULCH - PLAN QUANTITY                   |                            |                            |
0240 620.54                 2300.000  M2  |       3.00000       6900.00|       3.00000       6900.00|
  STABILIZATION GEOTEXTILE                |                            |                            |
0250 620.58                  100.000  M2  |       4.00000        400.00|       3.50000        350.00|
  EROSION CONTROL GEOTEXTILE              |                            |                            |
0260 627.76                           LUMP|    3000.00000       3000.00|    7500.00000       7500.00|
  TEMPORARY PAVEMENT MARKING LINE, WHITE  |                            |                            |
  OR YELLOW                               |                            |                            |
0270 629.05                   10.000  MH  |      18.00000        180.00|      20.00000        200.00|
  HAND LABOR, STRAIGHT TIME               |                            |                            |
0280 631.12                   40.000  HR  |      65.00000       2600.00|      75.00000       3000.00|
  ALL PURPOSE EXCAVATOR (INCLUDING        |                            |                            |
  OPERATOR)                               |                            |                            |
0290 631.14                   10.000  HR  |      85.00000        850.00|      75.00000        750.00|
  GRADER (INCLUDING OPERATOR)             |                            |                            |
     LETTING DATE : 04/05/00                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/04/01
                                                                                                                   PAGE : 3
     LOCATION : FORKSTOWN TWP.                          TABULATION OF BIDS
                TWP A R 02 WELS
                                            CONTRACT ID : 009053.00
                                                          =========

====================================================================================================================================
                                          |(   1  ) 000022             |(   2   ) 000351            |(      )
                                          |THE LANE CONSTRUCTION CORP. |COUNTY CONC. & CONSTR. CO.  |
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0300 631.172                  60.000  HR  |      35.00000       2100.00|      40.00000       2400.00|
  TRUCK - LARGE (INCLUDING OPERATOR)      |                            |                            |
0310 639.19                    1.000  EA  |    4000.00000       4000.00|    3500.00000       3500.00|
  FIELD OFFICE TYPE B                     |                            |                            |
0320 652.31                   10.000  EA  |      40.00000        400.00|      25.00000        250.00|
  TYPE I BARRICADE                        |                            |                            |
0330 652.33                   10.000  EA  |      40.00000        400.00|      35.00000        350.00|
  DRUM                                    |                            |                            |
0340 652.34                   50.000  EA  |      25.00000       1250.00|      17.00000        850.00|
  CONE                                    |                            |                            |
0350 652.35                   90.000  M2  |      88.00000       7920.00|      90.00000       8100.00|
  CONSTRUCTION SIGNS                      |                            |                            |
0360 652.36                   75.000  CD  |      80.00000       6000.00|     100.00000       7500.00|
  MAINTENANCE OF TRAFFIC CONTROL DEVICES  |                            |                            |
0370 652.38                 1500.000  MH  |      14.00000      21000.00|      14.00000      21000.00|
  FLAGGER                                 |                            |                            |
0380 659.10                           LUMP|   30000.00000      30000.00|   40000.00000      40000.00|
  MOBILIZATION                            |                            |                            |
     SECTION TOTALS                       |             $    691,250.65|             $    817,802.40|              $          0.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
     CONTRACT TOTALS                      |             $    691,250.65|             $    817,802.40|              $
====================================================================================================================================