     LETTING DATE : 05/07/03                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 05/07/03
                                                                                                                   PAGE : 1
     COUNTIE(S): PENOBSCOT                              TABULATION OF BIDS
                                            CONTRACT ID : 010092.00                                     COMPLETION DATE : 09/15/03
                                                           =========
   PROJECT(S):  BR-1007(900)X           LOCATION(S): CARMEL                         MAINE STATE DEPARTMENT OF TRANSPORTATION
                STP-1009(200)X                       STETSON
                                                                                   A TRUE COPY : __________________________
                                                                                         TITLE : __________________________
                                                                                        ATTEST : ____________________________
CONTRACT DESCRIPTION :  TWO BRIDGE REPLACEMENTS                                                       NOTARY PUBLIC
  --------------------------------------------------------------------------------------------------------------------------
                                                                                                   TOTAL         % OVER
  RANK     VENDOR NO./NAME                                                                          BID           LOW BID
  --------------------------------------------------------------------------------------------------------------------------
   1   001934         MAINE EARTH                                                            $    445,475.10     100.0000%
   2   000304         LOU SILVER INC.                                                        $    531,142.45     119.2306%
   3   000118         STETSON & WATSON, J. V.                                                $    547,323.50     122.8629%
   4   000272         A & V CONSTRUCTION, CORP.                                              $    612,987.00     137.6030%
   5   000063         WYMAN & SIMPSON, INC.                                                  $    614,062.00     137.8443%
   6   000466         EMERY LEE & SONS, INC.                                                 $    695,746.00     156.1807%
====================================================================================================================================
                                          |(   1  ) 001934             |(   2  ) 000304             |(   3  ) 000118
                                          |MAINE EARTH                 |LOU SILVER INC.             |STETSON & WATSON, J. V.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001   BRIDGE ITEMS
                                          |                            |                            |
0010 202.19                    1.000  LS  |    8500.00000       8500.00|   14390.00000      14390.00|   50000.00000       50000.00
  REMOVING EXISTING BRIDGE                |                            |                            |
0020 203.20                 1480.000  M3  |       7.00000      10360.00|      11.70000      17316.00|      11.00000       16280.00
  COMMON EXCAVATION                       |                            |                            |
0030 203.231                  76.000  M3  |      85.00000       6460.00|      50.00000       3800.00|     200.00000       15200.00
  DISPOSAL OF RIVERBED EXCAVATION         |                            |                            |
0040 203.24                   20.000  M3  |      20.00000        400.00|      14.25000        285.00|      15.00000         300.00
  COMMON BORROW                           |                            |                            |
0050 203.25                  800.000  M3  |      24.50000      19600.00|      20.50000      16400.00|      20.00000       16000.00
  GRANULAR BORROW                         |                            |                            |
0060 206.061                 540.000  M3  |      42.00000      22680.00|      21.90000      11826.00|      20.00000       10800.00
  STRUCTURAL EARTH EXCAVATION - DRAINAGE  |                            |                            |
  AND MINOR STRUCTURES, BELOW GRADE       |                            |                            |
0070 304.10                 1715.000  M3  |      17.00000      29155.00|      21.60000      37044.00|      20.00000       34300.00
  AGGREGATE SUBBASE COURSE - GRAVEL       |                            |                            |
0080 403.207                 179.000  MG  |      55.00000       9845.00|      55.00000       9845.00|      55.00000        9845.00
  HOT MIX ASPHALT 19.0 MM NOMINAL MAX SIZ |                            |                            |
0090 403.208                 229.000  MG  |      55.00000      12595.00|      55.00000      12595.00|      55.00000       12595.00
  HOT MIX ASPHALT 12.5 MM, SURFACE        |                            |                            |
0100 403.213                 120.000  MG  |      55.00000       6600.00|      55.00000       6600.00|      55.00000        6600.00
  HOT MIX ASPHALT 12.5 MM, BASE           |                            |                            |
     LETTING DATE : 05/07/03                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 05/07/03
                                                                                                                   PAGE : 2
     COUNTIE(S): PENOBSCOT                              TABULATION OF BIDS
                                            CONTRACT ID : 010092.00
                                                           =========
====================================================================================================================================
                                          |(   1  ) 001934             |(   2   ) 000304            |(   3  ) 000118
                                          |MAINE EARTH                 |LOU SILVER INC.             |STETSON & WATSON, J. V.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0110 409.15                  111.000  L   |       3.50000        388.50|       3.50000        388.50|       3.50000         388.50
  BITUMINOUS TACK COAT APPLIED            |                            |                            |
0120 509.411                          LUMP|  113000.00000     113000.00|  120900.00000     120900.00|  150000.00000      150000.00
  ALUMINUM STRUCTURAL PLATE BOX CULVERT   |                            |                            |
0130 509.43                    1.000  LS  |   93000.00000      93000.00|   81900.00000      81900.00|  100000.00000      100000.00
  METAL STRUCTURAL PLATE BOX CULVERT      |                            |                            |
0140 511.07                           LUMP|    5000.00000       5000.00|    2000.00000       2000.00|    5000.00000        5000.00
  COFFERDAM: DOWNSTREAM - BUSIELL BRIDGE  |                            |                            |
0150 511.07                           LUMP|    5000.00000       5000.00|    7500.00000       7500.00|    5000.00000        5000.00
  COFFERDAM: DOWNSTREAM - RIGGLES BRIDGE  |                            |                            |
0160 511.07                           LUMP|    5000.00000       5000.00|   10000.00000      10000.00|    5000.00000        5000.00
  COFFERDAM: UPSTREAM - BUSIELL BRIDGE    |                            |                            |
0170 511.07                           LUMP|    5000.00000       5000.00|   40000.00000      40000.00|    5000.00000        5000.00
  COFFERDAM: UPSTREAM - RIGGLES BRIDGE    |                            |                            |
0180 526.301                  36.000  LS  |    3200.00000       3200.00|    1050.00000       1050.00|    2000.00000        2000.00
  TEMPORARY CONCRETE BARRIER TYPE I       |                            |                            |
0190 603.17                   31.000  M   |      70.00000       2170.00|      67.30000       2086.30|      30.00000         930.00
  450 MM CULVERT PIPE OPTION I            |                            |                            |
0200 606.265                   4.000  EA  |      40.00000        160.00|      50.00000        200.00|      50.00000         200.00
  TERMINAL END - SINGLE RAIL - GALVANIZED |                            |                            |
  STEEL                                   |                            |                            |
0210 606.35                   12.000  EA  |      35.00000        420.00|      25.00000        300.00|      25.00000         300.00
  GUARDRAIL DELINEATOR POST               |                            |                            |
0220 606.47                    2.000  EA  |      40.00000         80.00|      35.00000         70.00|      35.00000          70.00
  SINGLE WOOD POST                        |                            |                            |
0230 606.55                  200.500  M   |      46.00000       9223.00|      28.71000       5756.36|      32.00000        6416.00
  GUARDRAIL TYPE 3 - SINGLE RAIL          |                            |                            |
0240 606.60                   30.500  M   |      40.00000       1220.00|      31.17000        950.69|      34.00000        1037.00
  GUARDRAIL TYPE 3 - OVER 4.5 METER RADIU |                            |                            |
0250 606.76                    4.000  EA  |    1500.00000       6000.00|    1400.00000       5600.00|    1400.00000        5600.00
  MODIFIED ECCENTRIC LOADER TERMINAL      |                            |                            |
0260 610.08                  200.000  M3  |      60.00000      12000.00|      52.80000      10560.00|      60.00000       12000.00
  PLAIN RIPRAP                            |                            |                            |
0270 610.18                    5.000  M3  |      50.00000        250.00|      70.00000        350.00|      60.00000         300.00
  STONE DITCH PROTECTION                  |                            |                            |
0280 613.319                  49.000  M2  |       3.00000        147.00|       2.40000        117.60|       2.00000          98.00
  EROSION CONTROL BLANKET                 |                            |                            |
0290 615.07                   65.000  M3  |      16.00000       1040.00|      39.50000       2567.50|      45.00000        2925.00
  LOAM                                    |                            |                            |
0300 618.1301                  1.000  UN  |      15.00000         15.00|     100.00000        100.00|     100.00000         100.00
  SEEDING METHOD NUMBER 1 - PLAN QUANTITY |                            |                            |
     LETTING DATE : 05/07/03                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 05/07/03
                                                                                                                   PAGE : 3
     COUNTIE(S): PENOBSCOT                              TABULATION OF BIDS
                                            CONTRACT ID : 010092.00
                                                           =========
====================================================================================================================================
                                          |(   1  ) 001934             |(   2   ) 000304            |(   3  ) 000118
                                          |MAINE EARTH                 |LOU SILVER INC.             |STETSON & WATSON, J. V.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0310 618.1411                 17.000  UN  |      15.00000        255.00|      39.00000        663.00|      40.00000         680.00
  SEEDING METHOD NUMBER 3 - PLAN QUANTITY |                            |                            |
0320 619.1201                 18.000  UN  |      15.00000        270.00|      20.00000        360.00|      20.00000         360.00
  MULCH - PLAN QUANTITY                   |                            |                            |
0330 619.1401                 10.000  M3  |      52.00000        520.00|      60.00000        600.00|      30.00000         300.00
  EROSION CONTROL MIX                     |                            |                            |
0340 620.54                  300.000  M2  |       1.05000        315.00|       4.00000       1200.00|       3.00000         900.00
  STABILIZATION GEOTEXTILE                |                            |                            |
0350 620.58                  218.000  M2  |       1.20000        261.60|       3.25000        708.50|       3.00000         654.00
  EROSION CONTROL GEOTEXTILE              |                            |                            |
0360 627.711                 860.000  M   |       1.25000       1075.00|       2.05000       1763.00|       2.05000        1763.00
  WHITE OR YELLOW PAINTED PAVEMENT        |                            |                            |
  MARKING LINE (PLAN QUANTITY )           |                            |                            |
0370 629.05                   20.000  HR  |      26.00000        520.00|      21.00000        420.00|      35.00000         700.00
  HAND LABOR, STRAIGHT TIME               |                            |                            |
0380 631.12                   10.000  HR  |      75.00000        750.00|     100.00000       1000.00|     100.00000        1000.00
  ALL PURPOSE EXCAVATOR (INCLUDING        |                            |                            |
  OPERATOR)                               |                            |                            |
0390 631.14                   10.000  HR  |     105.00000       1050.00|      90.00000        900.00|      85.00000         850.00
  GRADER (INCLUDING OPERATOR)             |                            |                            |
0400 631.15                   10.000  HR  |      55.00000        550.00|      80.00000        800.00|      65.00000         650.00
  ROLLER, EARTH AND BASE COURSE           |                            |                            |
  (INCLUDING OPERATOR)                    |                            |                            |
0410 631.171                  10.000  HR  |      40.00000        400.00|      58.00000        580.00|      45.00000         450.00
  TRUCK - SMALL (INCLUDING OPERATOR)      |                            |                            |
0420 637.071                          LUMP|    4000.00000       4000.00|     500.00000        500.00|    1000.00000        1000.00
  DUST CONTROL                            |                            |                            |
0430 652.39                           LUMP|    5000.00000       5000.00|   57750.00000      57750.00|    6000.00000        6000.00
  WORK ZONE TRAFFIC CONTROL               |                            |                            |
0440 656.75                           LUMP|   10000.00000      10000.00|    4460.00000       4460.00|    3000.00000        3000.00
  TEMPORARY SOIL EROSION AND WATER        |                            |                            |
  POLLUTION CONTROL                       |                            |                            |
0450 659.10                           LUMP|   32000.00000      32000.00|   36940.00000      36940.00|   54732.00000       54732.00
  MOBILIZATION                            |                            |                            |
     SECTION TOTALS                       |             $    445,475.10|             $    531,142.45|              $    547,323.50
------------------------------------------+----------------------------+----------------------------+-------------------------------
     CONTRACT TOTALS                      |             $    445,475.10|             $    531,142.45|              $    547,323.50
====================================================================================================================================
     LETTING DATE : 05/07/03                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 05/07/03
                                                                                                                   PAGE : 4
     COUNTIE(S): PENOBSCOT                              TABULATION OF BIDS
                                            CONTRACT ID : 010092.00
                                                           =========
====================================================================================================================================
                                          |(   4  ) 000272             |(   5   ) 000063            |(   6  ) 000466
                                          |A & V CONSTRUCTION, CORP.   |WYMAN & SIMPSON, INC.       |EMERY LEE & SONS, INC.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001   BRIDGE ITEMS
                                          |                            |                            |
0010 202.19                    1.000  LS  |   65000.00000      65000.00|   24000.00000      24000.00|   50000.00000       50000.00
  REMOVING EXISTING BRIDGE                |                            |                            |
0020 203.20                 1480.000  M3  |      13.00000      19240.00|       9.00000      13320.00|      11.00000       16280.00
  COMMON EXCAVATION                       |                            |                            |
0030 203.231                  76.000  M3  |     120.00000       9120.00|      85.00000       6460.00|      50.00000        3800.00
  DISPOSAL OF RIVERBED EXCAVATION         |                            |                            |
0040 203.24                   20.000  M3  |      27.00000        540.00|      15.00000        300.00|      25.00000         500.00
  COMMON BORROW                           |                            |                            |
0050 203.25                  800.000  M3  |      33.00000      26400.00|      22.00000      17600.00|      18.00000       14400.00
  GRANULAR BORROW                         |                            |                            |
0060 206.061                 540.000  M3  |      30.00000      16200.00|       9.00000       4860.00|      20.00000       10800.00
  STRUCTURAL EARTH EXCAVATION - DRAINAGE  |                            |                            |
  AND MINOR STRUCTURES, BELOW GRADE       |                            |                            |
0070 304.10                 1715.000  M3  |      28.00000      48020.00|      17.40000      29841.00|      20.00000       34300.00
  AGGREGATE SUBBASE COURSE - GRAVEL       |                            |                            |
0080 403.207                 179.000  MG  |      56.00000      10024.00|      78.00000      13962.00|      95.00000       17005.00
  HOT MIX ASPHALT 19.0 MM NOMINAL MAX SIZ |                            |                            |
0090 403.208                 229.000  MG  |      56.00000      12824.00|      78.00000      17862.00|      95.00000       21755.00
  HOT MIX ASPHALT 12.5 MM, SURFACE        |                            |                            |
0100 403.213                 120.000  MG  |      56.00000       6720.00|      78.00000       9360.00|      95.00000       11400.00
  HOT MIX ASPHALT 12.5 MM, BASE           |                            |                            |
0110 409.15                  111.000  L   |       4.00000        444.00|       4.00000        444.00|       6.00000         666.00
  BITUMINOUS TACK COAT APPLIED            |                            |                            |
0120 509.411                          LUMP|  120000.00000     120000.00|  170000.00000     170000.00|  147000.00000      147000.00
  ALUMINUM STRUCTURAL PLATE BOX CULVERT   |                            |                            |
0130 509.43                    1.000  LS  |  100000.00000     100000.00|  125000.00000     125000.00|  125000.00000      125000.00
  METAL STRUCTURAL PLATE BOX CULVERT      |                            |                            |
0140 511.07                           LUMP|    4750.00000       4750.00|    5000.00000       5000.00|   12000.00000       12000.00
  COFFERDAM: DOWNSTREAM - BUSIELL BRIDGE  |                            |                            |
0150 511.07                           LUMP|    8530.00000       8530.00|    5000.00000       5000.00|   12000.00000       12000.00
  COFFERDAM: DOWNSTREAM - RIGGLES BRIDGE  |                            |                            |
0160 511.07                           LUMP|   15700.00000      15700.00|    5000.00000       5000.00|   12000.00000       12000.00
  COFFERDAM: UPSTREAM - BUSIELL BRIDGE    |                            |                            |
0170 511.07                           LUMP|    3290.00000       3290.00|    5000.00000       5000.00|   12000.00000       12000.00
  COFFERDAM: UPSTREAM - RIGGLES BRIDGE    |                            |                            |
0180 526.301                  36.000  LS  |    6790.00000       6790.00|    4000.00000       4000.00|   20000.00000       20000.00
  TEMPORARY CONCRETE BARRIER TYPE I       |                            |                            |
0190 603.17                   31.000  M   |      76.00000       2356.00|      80.00000       2480.00|     125.00000        3875.00
  450 MM CULVERT PIPE OPTION I            |                            |                            |
     LETTING DATE : 05/07/03                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 05/07/03
                                                                                                                   PAGE : 5
     COUNTIE(S): PENOBSCOT                              TABULATION OF BIDS
                                            CONTRACT ID : 010092.00
                                                           =========
====================================================================================================================================
                                          |(   4  ) 000272             |(   5   ) 000063            |(   6  ) 000466
                                          |A & V CONSTRUCTION, CORP.   |WYMAN & SIMPSON, INC.       |EMERY LEE & SONS, INC.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0200 606.265                   4.000  EA  |      51.00000        204.00|      54.00000        216.00|      50.00000         200.00
  TERMINAL END - SINGLE RAIL - GALVANIZED |                            |                            |
  STEEL                                   |                            |                            |
0210 606.35                   12.000  EA  |      25.00000        300.00|      27.00000        324.00|      32.00000         384.00
  GUARDRAIL DELINEATOR POST               |                            |                            |
0220 606.47                    2.000  EA  |      35.00000         70.00|      38.00000         76.00|      65.00000         130.00
  SINGLE WOOD POST                        |                            |                            |
0230 606.55                  200.500  M   |      29.00000       5814.50|      32.00000       6416.00|      40.00000        8020.00
  GUARDRAIL TYPE 3 - SINGLE RAIL          |                            |                            |
0240 606.60                   30.500  M   |      31.00000        945.50|      34.00000       1037.00|      50.00000        1525.00
  GUARDRAIL TYPE 3 - OVER 4.5 METER RADIU |                            |                            |
0250 606.76                    4.000  EA  |    1420.00000       5680.00|    1500.00000       6000.00|    1500.00000        6000.00
  MODIFIED ECCENTRIC LOADER TERMINAL      |                            |                            |
0260 610.08                  200.000  M3  |      59.00000      11800.00|      52.00000      10400.00|      60.00000       12000.00
  PLAIN RIPRAP                            |                            |                            |
0270 610.18                    5.000  M3  |      71.00000        355.00|      73.00000        365.00|      60.00000         300.00
  STONE DITCH PROTECTION                  |                            |                            |
0280 613.319                  49.000  M2  |       3.00000        147.00|       3.00000        147.00|       3.00000         147.00
  EROSION CONTROL BLANKET                 |                            |                            |
0290 615.07                   65.000  M3  |      35.00000       2275.00|      36.00000       2340.00|      45.00000        2925.00
  LOAM                                    |                            |                            |
0300 618.1301                  1.000  UN  |      51.00000         51.00|      60.00000         60.00|     200.00000         200.00
  SEEDING METHOD NUMBER 1 - PLAN QUANTITY |                            |                            |
0310 618.1411                 17.000  UN  |      51.00000        867.00|      55.00000        935.00|     600.00000       10200.00
  SEEDING METHOD NUMBER 3 - PLAN QUANTITY |                            |                            |
0320 619.1201                 18.000  UN  |      15.00000        270.00|      15.00000        270.00|      10.00000         180.00
  MULCH - PLAN QUANTITY                   |                            |                            |
0330 619.1401                 10.000  M3  |      40.00000        400.00|      55.00000        550.00|      65.00000         650.00
  EROSION CONTROL MIX                     |                            |                            |
0340 620.54                  300.000  M2  |       4.00000       1200.00|       2.50000        750.00|       3.00000         900.00
  STABILIZATION GEOTEXTILE                |                            |                            |
0350 620.58                  218.000  M2  |       5.00000       1090.00|       2.50000        545.00|       3.00000         654.00
  EROSION CONTROL GEOTEXTILE              |                            |                            |
0360 627.711                 860.000  M   |       2.00000       1720.00|       2.20000       1892.00|       5.00000        4300.00
  WHITE OR YELLOW PAINTED PAVEMENT        |                            |                            |
  MARKING LINE (PLAN QUANTITY )           |                            |                            |
0370 629.05                   20.000  HR  |      35.00000        700.00|      25.00000        500.00|      20.00000         400.00
  HAND LABOR, STRAIGHT TIME               |                            |                            |
0380 631.12                   10.000  HR  |     110.00000       1100.00|      80.00000        800.00|      65.00000         650.00
  ALL PURPOSE EXCAVATOR (INCLUDING        |                            |                            |
  OPERATOR)                               |                            |                            |
     LETTING DATE : 05/07/03                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 05/07/03
                                                                                                                   PAGE : 6
     COUNTIE(S): PENOBSCOT                              TABULATION OF BIDS
                                            CONTRACT ID : 010092.00
                                                           =========
====================================================================================================================================
                                          |(   4  ) 000272             |(   5   ) 000063            |(   6  ) 000466
                                          |A & V CONSTRUCTION, CORP.   |WYMAN & SIMPSON, INC.       |EMERY LEE & SONS, INC.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0390 631.14                   10.000  HR  |     140.00000       1400.00|      65.00000        650.00|      85.00000         850.00
  GRADER (INCLUDING OPERATOR)             |                            |                            |
0400 631.15                   10.000  HR  |      66.00000        660.00|      45.00000        450.00|      85.00000         850.00
  ROLLER, EARTH AND BASE COURSE           |                            |                            |
  (INCLUDING OPERATOR)                    |                            |                            |
0410 631.171                  10.000  HR  |      61.00000        610.00|      35.00000        350.00|      50.00000         500.00
  TRUCK - SMALL (INCLUDING OPERATOR)      |                            |                            |
0420 637.071                          LUMP|    7950.00000       7950.00|    2000.00000       2000.00|    2000.00000        2000.00
  DUST CONTROL                            |                            |                            |
0430 652.39                           LUMP|   15900.00000      15900.00|   50000.00000      50000.00|   50000.00000       50000.00
  WORK ZONE TRAFFIC CONTROL               |                            |                            |
0440 656.75                           LUMP|   15530.00000      15530.00|    6500.00000       6500.00|   15000.00000       15000.00
  TEMPORARY SOIL EROSION AND WATER        |                            |                            |
  POLLUTION CONTROL                       |                            |                            |
0450 659.10                           LUMP|   60000.00000      60000.00|   61000.00000      61000.00|   52000.00000       52000.00
  MOBILIZATION                            |                            |                            |
     SECTION TOTALS                       |             $    612,987.00|             $    614,062.00|              $    695,746.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
     CONTRACT TOTALS                      |             $    612,987.00|             $    614,062.00|              $    695,746.00
====================================================================================================================================