LETTING DATE : 11/19/03 MAINE DEPARTMENT OF TRANSPORTATION DATE : 11/19/03
PAGE : 1
COUNTIE(S): CUMBERLAND TABULATION OF BIDS
CONTRACT ID : 010171.00 COMPLETION DATE : 10/15/04
=========
PROJECT(S): STP-1017(100)X LOCATION(S): WINDHAM MAINE STATE DEPARTMENT OF TRANSPORTATION
A TRUE COPY : __________________________
TITLE : __________________________
ATTEST : ____________________________ CONTRACT DESCRIPTION : CULVERT REHABILITATION NOTARY PUBLIC
--------------------------------------------------------------------------------------------------------------------------
TOTAL % OVER
RANK VENDOR NO./NAME BID LOW BID
--------------------------------------------------------------------------------------------------------------------------
1 000416 T BUCK CONSTRUCTION INC. $ 99,435.00 100.0000%
2 001954 TECHNICAL CONSTRUCTION LLC $ 126,140.00 126.8567%
3 000164 C P M CONSTRUCTORS $ 142,220.00 143.0281%
====================================================================================================================================
|( 1 ) 000416 |( 2 ) 001954 |( 3 ) 000164
|T BUCK CONSTRUCTION INC. |TECHNICAL CONSTRUCTION LLC |C P M CONSTRUCTORS
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001 BRIDGE ITEMS
| | |
0010 206.061 38.000 M3 | 12.50000 475.00| 90.00000 3420.00| 50.00000 1900.00
STRUCTURAL EARTH EXCAVATION - DRAINAGE | | |
AND MINOR STRUCTURES, BELOW GRADE | | |
0020 502.325 LUMP| 48500.00000 48500.00| 70000.00000 70000.00| 70000.00000 70000.00
STRUCTURAL CONCRETE CULVERT INVERT | | |
LINING | | |
0030 503.12 2440.000 KG | 1.25000 3050.00| 1.00000 2440.00| 1.00000 2440.00
REINFORCING STEEL, FABRICATED AND | | |
DELIVERED | | |
0040 503.13 2440.000 KG | 1.50000 3660.00| 2.00000 4880.00| 2.00000 4880.00
REINFORCING STEEL, PLACING | | |
0050 511.07 LUMP| 11500.00000 11500.00| 10000.00000 10000.00| 10000.00000 10000.00
COFFERDAM: 1 | | |
0060 511.07 LUMP| 6500.00000 6500.00| 4200.00000 4200.00| 10000.00000 10000.00
COFFERDAM: 2 | | |
0070 610.09 20.000 M3 | 185.00000 3700.00| 110.00000 2200.00| 250.00000 5000.00
HAND LAID RIPRAP | | |
0080 652.39 LUMP| 8600.00000 8600.00| 12400.00000 12400.00| 20000.00000 20000.00
WORK ZONE TRAFFIC CONTROL | | |
0090 656.75 LUMP| 3100.00000 3100.00| 5700.00000 5700.00| 5000.00000 5000.00
TEMPORARY SOIL EROSION AND WATER | | |
POLLUTION CONTROL | | |
0100 659.10 LUMP| 10350.00000 10350.00| 10900.00000 10900.00| 13000.00000 13000.00
MOBILIZATION | | |
SECTION TOTALS | $ 99,435.00| $ 126,140.00| $ 142,220.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
CONTRACT TOTALS | $ 99,435.00| $ 126,140.00| $ 142,220.00
====================================================================================================================================