LETTING DATE : 03/10/04 MAINE DEPARTMENT OF TRANSPORTATION DATE : 03/10/04
PAGE : 1
COUNTIE(S): PENOBSCOT TABULATION OF BIDS
CONTRACT ID : 011273.00 COMPLETION DATE : 08/13/04
=========
PROJECT(S): STP-1127(300)X LOCATION(S): LINCOLN-LEE MAINE STATE DEPARTMENT OF TRANSPORTATION
STP-1127(500)X SPRINGFIELD
A TRUE COPY : __________________________
TITLE : __________________________
ATTEST : ____________________________ CONTRACT DESCRIPTION : LEVEL 2 NOTARY PUBLIC
--------------------------------------------------------------------------------------------------------------------------
TOTAL % OVER
RANK VENDOR NO./NAME BID LOW BID
--------------------------------------------------------------------------------------------------------------------------
1 000022 LANE CONSTRUCTION CORP. (THE) $ 1,334,744.60 100.0000%
2 001195 VAUGHN THIBODEAU & SONS, INC. $ 2,125,668.20 159.2565%
====================================================================================================================================
|( 1 ) 000022 |( 2 ) 001195 |( )
|LANE CONSTRUCTION CORP. (TH |VAUGHN THIBODEAU & SONS, IN |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001 HIGHWAY ITEMS
| | |
0010 202.203 240.000 SY | 12.00000 2880.00| 13.00000 3120.00|
PAVEMENT BUTT JOINTS | | |
0020 204.41 18000.000 SY | 2.35000 42300.00| 4.95000 89100.00|
REHABILITATION OF EXISTING SHOULDERS, | | |
PLAN QUANTITY | | |
0030 211.20 21800.000 LF | 2.00000 43600.00| 2.40000 52320.00|
INSLOPE EXCAVATION | | |
0040 211.30 16400.000 LF | 3.00000 49200.00| 2.90000 47560.00|
DITCH EXCAVATION | | |
0050 304.103 2500.000 CY | 13.00000 32500.00| 20.00000 50000.00|
AGGREGATE SUBBASE - GRAVEL (TRUCK | | |
MEASURE) | | |
0060 309.36 61390.000 SY | 6.20000 380618.00| 9.50000 583205.00|
FULL DEPTH REC PAVEMENT W/FOAM ASPHALT | | |
6 INCH DEPTH | | |
0070 403.209 80.000 T | 85.00000 6800.00| 120.00000 9600.00|
HOT MIX ASPHALT 9.5 MM HMA (SIDEWALKS | | |
DRIVES, INCIDENT ALS) | | |
0080 403.210 6550.000 T | 37.90000 248245.00| 65.00000 425750.00|
HOT MIX ASPHALT 9.5 MM HMA | | |
0090 403.211 460.000 T | 40.00000 18400.00| 65.00000 29900.00|
HOT MIX ASPHALT (SHIMMING) | | |
0100 403.213 7630.000 T | 37.00000 282310.00| 65.00000 495950.00|
HOT MIX ASPHALT 12.5 MM HMA BASE | | |
LETTING DATE : 03/10/04 MAINE DEPARTMENT OF TRANSPORTATION DATE : 03/10/04
PAGE : 2
COUNTIE(S): PENOBSCOT TABULATION OF BIDS
CONTRACT ID : 011273.00
=========
====================================================================================================================================
|( 1 ) 000022 |( 2 ) 001195 |( )
|LANE CONSTRUCTION CORP. (TH |VAUGHN THIBODEAU & SONS, IN |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0110 409.15 2830.000 G | 3.00000 8490.00| 5.00000 14150.00|
BITUMINOUS TACK COAT APPLIED | | |
0120 411.10 90.000 CY | 45.00000 4050.00| 55.00000 4950.00|
UNTREATED AGGREGATE SURFACE COURSE | | |
(TRUCK MEASURE) | | |
0130 603.16 288.000 LF | 35.00000 10080.00| 44.00000 12672.00|
15 INCH CULVERT PIPE OPTION I | | |
0140 603.17 36.000 LF | 40.00000 1440.00| 46.20000 1663.20|
18 INCH CULVERT PIPE OPTION I | | |
0150 603.179 408.000 LF | 75.00000 30600.00| 60.50000 24684.00|
18 INCH CULVERT PIPE OPTION III | | |
0160 603.199 76.000 LF | 80.00000 6080.00| 77.00000 5852.00|
24 INCH CULVERT PIPE OPTION III | | |
0170 606.47 15.000 EA | 17.00000 255.00| 40.00000 600.00|
SINGLE WOOD POST | | |
0180 610.08 20.000 CY | 60.00000 1200.00| 55.00000 1100.00|
PLAIN RIPRAP | | |
0190 613.319 7250.000 SY | 2.50000 18125.00| 2.25000 16312.50|
EROSION CONTROL BLANKET | | |
0200 615.07 65.000 CY | 45.00000 2925.00| 38.50000 2502.50|
LOAM | | |
0210 618.1301 5.000 UN | 28.00000 140.00| 75.00000 375.00|
SEEDING METHOD NUMBER 1 - PLAN QUANTITY | | |
0220 618.1401 460.000 UN | 11.46000 5271.60| 42.00000 19320.00|
SEEDING METHOD NUMBER 2 - PLAN QUANTITY | | |
0230 619.1201 465.000 UN | 6.00000 2790.00| 32.00000 14880.00|
MULCH - PLAN QUANTITY | | |
0240 620.58 80.000 SY | 4.00000 320.00| 11.00000 880.00|
EROSION CONTROL GEOTEXTILE | | |
0250 627.76 LUMP| 5000.00000 5000.00| 8000.00000 8000.00|
TEMPORARY PVMT. MARK LINE, W OR YELLOW | | |
0260 629.05 30.000 HR | 25.00000 750.00| 33.00000 990.00|
HAND LABOR, STRAIGHT TIME | | |
0270 631.10 10.000 HR | 35.00000 350.00| 44.00000 440.00|
AIR COMPRESSOR (INCLUDING OPERATOR) | | |
0280 631.11 10.000 HR | 35.00000 350.00| 33.00000 330.00|
AIR TOOL (INCLUDING OPERATOR) | | |
0290 631.111 30.000 HR | 180.00000 5400.00| 275.00000 8250.00|
TRACTOR MOUNTED HYDRAULIC HAMMER | | |
0300 631.12 25.000 HR | 85.00000 2125.00| 110.00000 2750.00|
ALL PURPOSE EXCAVATOR (INCLUDING | | |
OPERATOR) | | |
LETTING DATE : 03/10/04 MAINE DEPARTMENT OF TRANSPORTATION DATE : 03/10/04
PAGE : 3
COUNTIE(S): PENOBSCOT TABULATION OF BIDS
CONTRACT ID : 011273.00
=========
====================================================================================================================================
|( 1 ) 000022 |( 2 ) 001195 |( )
|LANE CONSTRUCTION CORP. (TH |VAUGHN THIBODEAU & SONS, IN |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0310 631.172 30.000 HR | 45.00000 1350.00| 49.50000 1485.00|
TRUCK - LARGE (INCLUDING OPERATOR) | | |
0320 631.18 2.000 HR | 25.00000 50.00| 38.50000 77.00|
CHAIN SAW RENTAL (INCLUDING OPERATOR) | | |
0330 631.32 50.000 HR | 120.00000 6000.00| 132.00000 6600.00|
CULVERT CLEANER (INCLUDING OPERATOR) | | |
0340 639.19 1.000 EA | 7000.00000 7000.00| 9000.00000 9000.00|
FIELD OFFICE TYPE B | | |
0350 652.38 2850.000 HR | 15.00000 42750.00| 18.00000 51300.00|
FLAGGER | | |
0360 652.39 LUMP| 15000.00000 15000.00| 12000.00000 12000.00|
WORK ZONE TRAFFIC CONTROL | | |
0370 656.75 LUMP| 5000.00000 5000.00| 18000.00000 18000.00|
TEMPORARY SOIL EROSION AND WATER | | |
POLLUTION CONTROL | | |
0380 659.10 LUMP| 45000.00000 45000.00| 100000.00000 100000.00|
MOBILIZATION | | |
SECTION TOTALS | $ 1,334,744.60| $ 2,125,668.20| $ 0.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
CONTRACT TOTALS | $ 1,334,744.60| $ 2,125,668.20| $
====================================================================================================================================