LETTING DATE : 06/30/04 MAINE DEPARTMENT OF TRANSPORTATION DATE : 06/30/04
PAGE : 1
COUNTIE(S): LINCOLN TABULATION OF BIDS
CONTRACT ID : 011964.00 COMPLETION DATE : 10/16/04
=========
PROJECT(S): 011964.00 LOCATION(S): BOOTHBAY, COUNTRY CLUB RD. MAINE STATE DEPARTMENT OF TRANSPORTATION
A TRUE COPY : __________________________
TITLE : __________________________
ATTEST : ____________________________ CONTRACT DESCRIPTION : BOOTHBAY, HIGHWAY RECONSTRUCTION NOTARY PUBLIC
--------------------------------------------------------------------------------------------------------------------------
TOTAL % OVER
RANK VENDOR NO./NAME BID LOW BID
--------------------------------------------------------------------------------------------------------------------------
1 000059 PIKE INDUSTRIES, INC. $ 469,885.10 100.0000%
2 000050 MARRINERS, INC. $ 475,438.25 101.1818%
====================================================================================================================================
|( 1 ) 000059 |( 2 ) 000050 |( )
|PIKE INDUSTRIES, INC. |MARRINERS, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001 HIGHWAY ITEMS
| | |
0010 202.203 140.000 SY | 20.00000 2800.00| 25.00000 3500.00|
PAVEMENT BUTT JOINTS | | |
0020 203.20 75.000 CY | 35.00000 2625.00| 18.00000 1350.00|
COMMON EXCAVATION | | |
0030 203.21 50.000 CY | 112.50000 5625.00| 80.00000 4000.00|
ROCK EXCAVATION | | |
0040 203.24 200.000 CY | 17.50000 3500.00| 25.00000 5000.00|
COMMON BORROW | | |
0050 204.41 300.000 SY | 7.50000 2250.00| 15.00000 4500.00|
REHABILITATION OF EXISTING SHOULDERS, | | |
PLAN QUANTITY | | |
0060 206.07 50.000 CY | 165.00000 8250.00| 200.00000 10000.00|
STRUCTURAL ROCK EXCAVATION - DRAINAGE | | |
AND MINOR STRUCTURES | | |
0070 211.21 600.000 LF | 6.00000 3600.00| 10.00000 6000.00|
INSLOPE REHABILITATION | | |
0080 211.30 1100.000 LF | 4.50000 4950.00| 5.00000 5500.00|
DITCH EXCAVATION | | |
0090 211.40 360.000 LF | 15.75000 5670.00| 60.00000 21600.00|
NEW DITCH EXCAVATION | | |
0100 304.103 300.000 CY | 42.50000 12750.00| 40.00000 12000.00|
AGGREGATE SUBBASE - GRAVEL (TRUCK | | |
MEASURE) | | |
0110 304.104 2000.000 CY | 28.50000 57000.00| 25.00000 50000.00|
AGGREGATE SUBBASE COURSE (PLAN QUANTITY | | |
LETTING DATE : 06/30/04 MAINE DEPARTMENT OF TRANSPORTATION DATE : 06/30/04
PAGE : 2
COUNTIE(S): LINCOLN TABULATION OF BIDS
CONTRACT ID : 011964.00
=========
====================================================================================================================================
|( 1 ) 000059 |( 2 ) 000050 |( )
|PIKE INDUSTRIES, INC. |MARRINERS, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0120 307.32 6970.000 SY | 2.75000 19167.50| 2.00000 13940.00|
FULL DEPTH RECYCLED PAVEMENT(UNTREATED | | |
MAINELINE TRAVELWAY) | | |
0130 403.209 50.000 T | 95.00000 4750.00| 100.00000 5000.00|
HOT MIX ASPHALT 9.5 MM HMA (SIDEWALKS | | |
DRIVES, INCIDENT ALS) | | |
0140 403.210 960.000 T | 55.30000 53088.00| 48.00000 46080.00|
HOT MIX ASPHALT 9.5 MM HMA | | |
0150 403.211 260.000 T | 67.50000 17550.00| 50.00000 13000.00|
HOT MIX ASPHALT (SHIMMING) | | |
0160 403.213 880.000 T | 50.50000 44440.00| 48.00000 42240.00|
HOT MIX ASPHALT 12.5 MM HMA BASE | | |
0170 409.15 300.000 G | 15.00000 4500.00| 6.00000 1800.00|
BITUMINOUS TACK COAT APPLIED | | |
0180 411.10 40.000 CY | 62.75000 2510.00| 50.00000 2000.00|
UNTREATED AGGREGATE SURFACE COURSE | | |
(TRUCK MEASURE) | | |
0190 603.16 353.000 LF | 26.50000 9354.50| 32.00000 11296.00|
15 INCH CULVERT PIPE OPTION I | | |
0200 603.169 263.000 LF | 56.50000 14859.50| 150.00000 39450.00|
15 INCH CULVERT PIPE OPTION III | | |
0210 603.17 34.000 LF | 27.50000 935.00| 85.00000 2890.00|
18 INCH CULVERT PIPE OPTION I | | |
0220 603.179 94.000 LF | 60.50000 5687.00| 85.00000 7990.00|
18 INCH CULVERT PIPE OPTION III | | |
0230 603.209 8.000 LF | 275.00000 2200.00| 100.00000 800.00|
30 INCH CULVERT PIPE OPTION III | | |
0240 604.167 2.000 EA | 550.00000 1100.00| 500.00000 1000.00|
ALTER CATCH BASIN GRATE TO CASCADE | | |
0250 604.247 2.000 EA | 1500.00000 3000.00| 1800.00000 3600.00|
CATCH BASIN TYPE F5-C | | |
0260 606.151 425.000 LF | 40.00000 17000.00| 38.07000 16179.75|
GUARDRAIL TYPE 3AA - SINGLE RAIL | | |
0270 606.35 3.000 EA | 31.50000 94.50| 40.00000 120.00|
GUARDRAIL DELINEATOR POST | | |
0280 606.7911 2.000 EA | 2400.00000 4800.00| 2300.00000 4600.00|
GUARDRAIL TYPE 3AA - 350 FLARED TERMINA | | |
0290 609.31 840.000 LF | 8.00000 6720.00| 8.00000 6720.00|
CURB TYPE 3 | | |
0300 610.08 20.000 CY | 55.00000 1100.00| 60.00000 1200.00|
PLAIN RIPRAP | | |
LETTING DATE : 06/30/04 MAINE DEPARTMENT OF TRANSPORTATION DATE : 06/30/04
PAGE : 3
COUNTIE(S): LINCOLN TABULATION OF BIDS
CONTRACT ID : 011964.00
=========
====================================================================================================================================
|( 1 ) 000059 |( 2 ) 000050 |( )
|PIKE INDUSTRIES, INC. |MARRINERS, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0310 610.18 22.000 CY | 37.50000 825.00| 40.00000 880.00|
STONE DITCH PROTECTION | | |
0320 613.319 230.000 SY | 1.00000 230.00| 3.00000 690.00|
EROSION CONTROL BLANKET | | |
0330 615.07 40.000 CY | 42.80000 1712.00| 75.00000 3000.00|
LOAM | | |
0340 618.1301 12.000 UN | 17.85000 214.20| 18.00000 216.00|
SEEDING METHOD NUMBER 1 - PLAN QUANTITY | | |
0350 618.1401 28.000 UN | 16.80000 470.40| 16.00000 448.00|
SEEDING METHOD NUMBER 2 - PLAN QUANTITY | | |
0360 619.1201 40.000 UN | 9.00000 360.00| 9.00000 360.00|
MULCH - PLAN QUANTITY | | |
0370 620.56 50.000 SY | 2.00000 100.00| 6.00000 300.00|
DRAINAGE GEOTEXTILE | | |
0380 627.711 4950.000 LF | 0.65000 3217.50| 0.63000 3118.50|
WHITE OR YELLOW PAINTED PAVEMENT | | |
MARKING LINE | | |
0390 629.05 8.000 HR | 45.00000 360.00| 25.00000 200.00|
HAND LABOR, STRAIGHT TIME | | |
0400 631.111 8.000 HR | 275.00000 2200.00| 200.00000 1600.00|
TRACTOR MOUNTED HYDRAULIC HAMMER | | |
0410 631.12 8.000 HR | 135.00000 1080.00| 100.00000 800.00|
ALL PURPOSE EXCAVATOR (INCLUDING | | |
OPERATOR) | | |
0420 631.14 24.000 HR | 125.00000 3000.00| 125.00000 3000.00|
GRADER (INCLUDING OPERATOR) | | |
0430 631.172 30.000 HR | 65.00000 1950.00| 45.00000 1350.00|
TRUCK - LARGE (INCLUDING OPERATOR) | | |
0440 631.18 16.000 HR | 65.00000 1040.00| 70.00000 1120.00|
CHAIN SAW RENTAL (INCLUDING OPERATOR) | | |
0450 639.19 1.000 EA | 5000.00000 5000.00| 8000.00000 8000.00|
FIELD OFFICE TYPE B | | |
0460 652.38 1000.000 HR | 14.75000 14750.00| 16.00000 16000.00|
FLAGGER | | |
0470 652.39 LUMP| 35000.00000 35000.00| 35000.00000 35000.00|
WORK ZONE TRAFFIC CONTROL | | |
0480 656.75 LUMP| 7500.00000 7500.00| 6000.00000 6000.00|
TEMPORARY SOIL EROSION AND WATER | | |
POLLUTION CONTROL | | |
0490 659.10 LUMP| 69000.00000 69000.00| 50000.00000 50000.00|
MOBILIZATION | | |
SECTION TOTALS | $ 469,885.10| $ 475,438.25| $ 0.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
CONTRACT TOTALS | $ 469,885.10| $ 475,438.25| $
====================================================================================================================================