     LETTING DATE : 07/03/02                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/10/02
                                                                                                                   PAGE : 1
     LOCATION :                                         TABULATION OF BIDS
                                            CONTRACT ID : 010209.00                                     COMPLETION DATE : 06/13/03
                                                          =========
   PROJECT(S):  STP-1020(900)X          COUNTIE(S) : KENNEBEC                       MAINE STATE DEPARTMENT OF TRANSPORTATION
                STP-1062(700)X
                STP-1062(800)X                                                     A TRUE COPY : __________________________
                                                                                         TITLE : __________________________
                                                                                        ATTEST : ____________________________
CONTRACT DESCRIPTION :  CHIP                                                                          NOTARY PUBLIC
  --------------------------------------------------------------------------------------------------------------------------
                                                                                                   TOTAL         % OVER
  RANK     VENDOR NO./NAME                                                                          BID           LOW BID
  --------------------------------------------------------------------------------------------------------------------------
   1   000059         PIKE INDUSTRIES, INC.                                                  $  1,444,854.25     100.0000%
   2   000855         BRIDGECORP                                                             $  1,577,171.20     109.1578%
   3   000272         A & V CONSTRUCTION, CORP.                                              $  1,596,460.00     110.4928%
====================================================================================================================================
                                          |(   1  ) 000059             |(   2  ) 000855             |(   3  ) 000272
                                          |PIKE INDUSTRIES, INC.       |BRIDGECORP                  |A & V CONSTRUCTION, CORP.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001   HIGHWAY ITEMS
                                          |                            |                            |
0010 201.24                   24.000  EA  |     300.00000       7200.00|      90.00000       2160.00|     200.00000        4800.00
  REMOVING STUMP                          |                            |                            |
0020 202.203                1325.000  M2  |      15.00000      19875.00|      20.00000      26500.00|      19.00000       25175.00
  PAVEMENT BUTT JOINTS                    |                            |                            |
0030 203.20                 1950.000  M3  |       8.00000      15600.00|       6.00000      11700.00|      12.00000       23400.00
  COMMON EXCAVATION                       |                            |                            |
0040 203.2021               2750.000  M   |       9.00000      24750.00|      10.00000      27500.00|       8.00000       22000.00
  INSLOPE REHABILITATION                  |                            |                            |
0050 203.203                4970.000  M   |      12.50000      62125.00|      12.00000      59640.00|      12.00000       59640.00
  DITCH EXCAVATION                        |                            |                            |
0060 203.204                 150.000  M   |      17.00000       2550.00|      15.00000       2250.00|      24.00000        3600.00
  NEW DITCH EXCAVATION                    |                            |                            |
0070 203.21                 1250.000  M3  |      44.00000      55000.00|       6.00000       7500.00|      40.00000       50000.00
  ROCK EXCAVATION                         |                            |                            |
0080 204.41                 9905.000  M2  |       4.75000      47048.75|       5.00000      49525.00|       4.50000       44572.50
  REHABILITATION OF EXISTING SHOULDERS,   |                            |                            |
  PLAN QUANTITY                           |                            |                            |
0090 205.41                 2200.000  M2  |      24.00000      52800.00|      22.50000      49500.00|      26.00000       57200.00
  RECONSTRUCTION OF EXISTING SHOULDER     |                            |                            |
  PLAN QUANTITY                           |                            |                            |
0100 304.103                 300.000  M3  |      26.00000       7800.00|      28.00000       8400.00|      27.00000        8100.00
  AGGREGATE SUBBASE - GRAVEL (TRUCK       |                            |                            |
  MEASURE)                                |                            |                            |
     LETTING DATE : 07/03/02                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/10/02
                                                                                                                   PAGE : 2
     LOCATION :                                         TABULATION OF BIDS
                                            CONTRACT ID : 010209.00
                                                          =========
====================================================================================================================================
                                          |(   1  ) 000059             |(   2   ) 000855            |(   3  ) 000272
                                          |PIKE INDUSTRIES, INC.       |BRIDGECORP                  |A & V CONSTRUCTION, CORP.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0110 304.104                1280.000  M3  |      21.00000      26880.00|      25.00000      32000.00|      21.00000       26880.00
  AGGREGATE SUBBASE COURSE - GRAVEL (PLAN |                            |                            |
  QUANTITY)                               |                            |                            |
0120 307.40                30425.000  M2  |       5.50000     167337.50|       6.50000     197762.50|       6.50000      197762.50
  COLD IN-PLACE RECYCLED PAVEMENT (WITH   |                            |                            |
  BITUMINOUS STABILIZER)                  |                            |                            |
0130 403.208                5450.000  MG  |      37.50000     204375.00|      38.00000     207100.00|      40.00000      218000.00
  HOT MIX ASPHALT 12.5 MM, SURFACE        |                            |                            |
0140 403.209                 280.000  MG  |      90.00000      25200.00|     116.00000      32480.00|      95.00000       26600.00
  HOT MIX ASPHALT 9.5 MM(SIDEWALKS,DRIVES |                            |                            |
  INCIDENTAL )                            |                            |                            |
0150 403.210                1075.000  MG  |      37.50000      40312.50|      38.00000      40850.00|      41.00000       44075.00
  HOT MIX ASPHALT 9.5 MM NOMINAL MAX SIZE |                            |                            |
0160 403.211                1275.000  MG  |      37.50000      47812.50|      38.00000      48450.00|      40.00000       51000.00
  HOT MIX ASPHALT (SHIM)                  |                            |                            |
0170 403.213                3825.000  MG  |      37.50000     143437.50|      38.00000     145350.00|      40.00000      153000.00
  HOT MIX ASPHALT 12.5 MM, BASE           |                            |                            |
0180 409.15                 7080.000  L   |       1.00000       7080.00|       1.25000       8850.00|       1.00000        7080.00
  BITUMINOUS TACK COAT APPLIED            |                            |                            |
0190 411.10                  135.000  M3  |      60.00000       8100.00|      75.00000      10125.00|      40.00000        5400.00
  UNTREATED AGGREGATE SURFACE COURSE      |                            |                            |
  (TRUCK MEASURE)                         |                            |                            |
0200 603.16                  314.400  M   |      60.00000      18864.00|      88.00000      27667.20|      65.00000       20436.00
  375 MM CULVERT PIPE OPTION I            |                            |                            |
0210 603.17                  191.900  M   |      75.00000      14392.50|      95.00000      18230.50|      70.00000       13433.00
  450 MM CULVERT PIPE OPTION I            |                            |                            |
0220 603.179                 138.600  M   |     250.00000      34650.00|     220.00000      30492.00|     160.00000       22176.00
  450 MM CULVERT PIPE OPTION III          |                            |                            |
0230 603.19                   45.700  M   |      95.00000       4341.50|     100.00000       4570.00|     100.00000        4570.00
  600 MM CULVERT PIPE OPTION I            |                            |                            |
0240 603.199                  22.600  M   |     400.00000       9040.00|     140.00000       3164.00|     350.00000        7910.00
  600 MM CULVERT PIPE OPTION III          |                            |                            |
0250 603.235                  19.500  M   |     390.00000       7605.00|     500.00000       9750.00|     550.00000       10725.00
  1200 MM REINFORCED CONCRETE PIPE CLASS  |                            |                            |
  III                                     |                            |                            |
0260 603.73                   14.000  M   |      70.00000        980.00|      10.00000        140.00|     160.00000        2240.00
  REMOVE AND RELAY METAL PIPE             |                            |                            |
0270 604.092                   9.000  EA  |    1450.00000      13050.00|    2100.00000      18900.00|    2100.00000       18900.00
  CATCH BASIN TYPE B1-C                   |                            |                            |
0280 604.166                   2.000  EA  |     750.00000       1500.00|     880.00000       1760.00|    1700.00000        3400.00
  REBUILDING MANHOLE                      |                            |                            |
     LETTING DATE : 07/03/02                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/10/02
                                                                                                                   PAGE : 3
     LOCATION :                                         TABULATION OF BIDS
                                            CONTRACT ID : 010209.00
                                                          =========
====================================================================================================================================
                                          |(   1  ) 000059             |(   2   ) 000855            |(   3  ) 000272
                                          |PIKE INDUSTRIES, INC.       |BRIDGECORP                  |A & V CONSTRUCTION, CORP.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0290 604.18                   12.000  EA  |     350.00000       4200.00|     300.00000       3600.00|     400.00000        4800.00
  ADJUSTING MANHOLE OR CATCH BASIN TO     |                            |                            |
  GRADE                                   |                            |                            |
0300 605.09                  215.000  M   |      60.00000      12900.00|      72.00000      15480.00|      90.00000       19350.00
  150 MM UNDERDRAIN TYPE B                |                            |                            |
0310 605.12                  180.000  M   |      66.00000      11880.00|      95.00000      17100.00|     100.00000       18000.00
  375 MM UNDERDRAIN TYPE C                |                            |                            |
0320 605.13                  110.000  M   |      68.00000       7480.00|     100.00000      11000.00|     130.00000       14300.00
  450 MM UNDERDRAIN TYPE C                |                            |                            |
0330 606.362                 400.000  M   |      13.50000       5400.00|      16.00000       6400.00|      13.00000        5200.00
  GUARDRAIL ADJUSTED                      |                            |                            |
0340 606.47                   25.000  EA  |      42.00000       1050.00|      48.00000       1200.00|      45.00000        1125.00
  SINGLE WOOD POST                        |                            |                            |
0350 609.31                 1035.000  M   |      15.00000      15525.00|      19.00000      19665.00|      15.00000       15525.00
  CURB TYPE 3                             |                            |                            |
0360 610.08                   65.000  M3  |      65.00000       4225.00|      85.00000       5525.00|      85.00000        5525.00
  PLAIN RIPRAP                            |                            |                            |
0370 610.18                  550.000  M3  |      44.00000      24200.00|      38.00000      20900.00|      55.00000       30250.00
  STONE DITCH PROTECTION                  |                            |                            |
0380 613.319                9250.000  M2  |       1.50000      13875.00|       1.75000      16187.50|       2.00000       18500.00
  EROSION CONTROL BLANKET                 |                            |                            |
0390 615.07                   75.000  M3  |      45.00000       3375.00|      48.00000       3600.00|      41.00000        3075.00
  LOAM                                    |                            |                            |
0400 618.1301                 32.500  UN  |      29.00000        942.50|      32.00000       1040.00|      25.00000         812.50
  SEEDING METHOD NUMBER 1 - PLAN QUANTITY |                            |                            |
0410 618.1401                302.500  UN  |      13.00000       3932.50|      15.00000       4537.50|      14.00000        4235.00
  SEEDING METHOD NUMBER 2 - PLAN QUANTITY |                            |                            |
0420 619.1201                335.000  UN  |       7.50000       2512.50|      12.00000       4020.00|       8.00000        2680.00
  MULCH - PLAN QUANTITY                   |                            |                            |
0430 620.58                 2000.000  M2  |       1.25000       2500.00|       2.50000       5000.00|       2.00000        4000.00
  EROSION CONTROL GEOTEXTILE              |                            |                            |
0440 627.75                   35.000  M2  |      15.00000        525.00|      15.00000        525.00|      27.00000         945.00
  WHITE OR YELLOW PAVEMENT AND CURB       |                            |                            |
  MARKING                                 |                            |                            |
0450 627.76                           LUMP|    5000.00000       5000.00|    1000.00000       1000.00|   11300.00000       11300.00
  TEMPORARY PAVEMENT MARKING LINE, WHITE  |                            |                            |
  OR YELLOW                               |                            |                            |
0460 629.05                   50.000  MH  |      35.00000       1750.00|      20.00000       1000.00|      35.00000        1750.00
  HAND LABOR, STRAIGHT TIME               |                            |                            |
0470 631.12                  105.000  HR  |     120.00000      12600.00|      60.00000       6300.00|     100.00000       10500.00
  ALL PURPOSE EXCAVATOR (INCLUDING        |                            |                            |
  OPERATOR)                               |                            |                            |
     LETTING DATE : 07/03/02                     MAINE DEPARTMENT OF TRANSPORTATION                                DATE : 12/10/02
                                                                                                                   PAGE : 4
     LOCATION :                                         TABULATION OF BIDS
                                            CONTRACT ID : 010209.00
                                                          =========
====================================================================================================================================
                                          |(   1  ) 000059             |(   2   ) 000855            |(   3  ) 000272
                                          |PIKE INDUSTRIES, INC.       |BRIDGECORP                  |A & V CONSTRUCTION, CORP.
LINE NO / ITEM CODE / ALT                 |                            |                            |
ITEM DESCRIPTION            QUANTITY      |  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT|  UNIT PRICE          AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
0480 631.172                 200.000  HR  |      65.00000      13000.00|      30.00000       6000.00|      40.00000        8000.00
  TRUCK - LARGE (INCLUDING OPERATOR)      |                            |                            |
0490 631.18                   45.000  HR  |      75.00000       3375.00|      30.00000       1350.00|      45.00000        2025.00
  CHAIN SAW RENTAL (INCLUDING OPERATOR)   |                            |                            |
0500 631.32                   30.000  HR  |     200.00000       6000.00|      80.00000       2400.00|     110.00000        3300.00
  CULVERT CLEANER (INCLUDING OPERATOR)    |                            |                            |
0510 639.18                    1.000  EA  |    5500.00000       5500.00|    4000.00000       4000.00|    6500.00000        6500.00
  FIELD OFFICE TYPE A                     |                            |                            |
0520 652.38                 4075.000  MH  |      12.00000      48900.00|       7.00000      28525.00|      14.50000       59087.50
  FLAGGER                                 |                            |                            |
0530 652.39                           LUMP|   35000.00000      35000.00|   16000.00000      16000.00|   29000.00000       29000.00
  WORK ZONE TRAFFIC CONTROL               |                            |                            |
0540 656.75                           LUMP|   12000.00000      12000.00|    7500.00000       7500.00|   44600.00000       44600.00
  TEMPORARY SOIL EROSION AND WATER        |                            |                            |
  POLLUTION CONTROL                       |                            |                            |
0550 659.10                           LUMP|  117500.00000     117500.00|  285000.00000     285000.00|  140000.00000      140000.00
  MOBILIZATION                            |                            |                            |
     SECTION TOTALS                       |             $  1,444,854.25|             $  1,577,171.20|              $  1,596,460.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
     CONTRACT TOTALS                      |             $  1,444,854.25|             $  1,577,171.20|              $  1,596,460.00
====================================================================================================================================